Our House Remodel

Our House

Project: Enlarge kitchen, add media room in a new lower floor, relocate guest bedroom to lower floor add bathroom on lower floor.

Final Results

downstairs
upstairs

Construction Started: April 9th, 2004.

Initial Estimated Project Completion Date: January 15th, 2005.

Actual Project Completion Date: June 6, 2005

Contractor: Bauman Construction

Craig Bauman

"The Boss"

Todd

Site Foreman

Bradley
Jose
Working hard! Reading the paper during lunch break.

 

Architect: Gary Kohlsaat

Interior Designer: Ann Fiorio

Pictures

NEW

Friday 5/5/2005: Updated Current Progress.

Friday 12/24: Updated Daily Log

Current Progress

Pictures of the final project

After taking several months to relax and live in the house we've now starting to finish up some final stuff and do the remaining decorating (window coverings, furniture, pictures etc). Below are links to things we've updated since completing the project:

Master Bathroom: (12/21/2005). We've started to finish the mirror area in our master bathroom.

Pam's Office: (12/14/2005) We finally finished the bookshelves in Pam's office!

Master Bedroom Curio: No progress yet but scheduled for week of 12/26.

Shelves for dinning room built-in: Spring 2006?