Progress as of 12/17

Cabinets: The cabinet installer (singular) was here Monday, Tuesday and Wednesday. Most of the kitchen cabinets are hung, the laundry room lower cabinet is in and the media room cabinets are here but not in place:

Kitchen:

End view of our (massive) island (Alan refers to it as the continent). The view is standing in the dinning room looking into the kitchen.

The cabinets along the window have a back shelf that we'll be able to put plants on.

View of stove top area from opposite end of the kitchen.

View of island from door end of the kitchen. It will have an additional overhang on this end for stools.

 

Stove/fridge wall. The large holes will have appliances in them. The upper holes will have glass and the middle cabinet doors are still being worked on.

Stairwell bench

Laundry room lower cabinet. Upper will be installed after counter top is in.

Media room cabinets are not yet installed should be done by Tuesday.

=

Guest Bath Tile: The tile installer and his helper have been working on the guest bathroom for a little over a week now - they should be done sometime next week. At this point they have most of it done except the floor and a few misc. pieces. Next they will start on the slate staircase, hall and media room.

View from the lower foyer into the guest room:

Views around the bathroom from the doorway looking first left, straight on and then right: