Daily Log
Click here to return to main Remodel page
November
Week 37: Tile, Cabinets, Wainscot
- 12/24:
Complete up bath wainscot and begin laying stairs slate.
- 12/23:
More doors, trim, wainscot, Black grout tuest bath tile prep for stairs.
- 12/22: Begin up bath wainscot. White grout Guest bath tile.
- 12/21: Details for media room bar installed, guest bath tile prep for grout.
- 12/20:
Media room bar install started, guest bath tile.
Week 36: Cabinets & Tile
- 12/17:
Granite measure, guest bath tile, meet with cabinet painter.
- 12/16: Kitchen uppers, laundry room and staircase cabinets installed. Guest
bath tile.
- 12/15: Kitchen stained cabinet installed. Guest bath tile.
- 12/14:
Cabinet install, guest bath tile.
- 12/13: More kitchen cabinet install, guest bath tile.
Week 35: Cabinets, Heat
- 12/10:
Temporary heat installed, temp lighting set-up.
- 12/9:
More cabinet install, begin tiling guest bath.
- 12/8:
First coat of stucco applied, Kitchen paint grade cabinet install, Guest bath
show floated
- 12/7:
Kitchen cabinet toe kicks installed, Stair railing redone.
- 12/6: Nothing
Week 34: Stairs, Trim, Paint
- 12/4: Paint prep, closet doors installed
- 12/3:
Meet with Kelley to go over problem wth balluster install - they will redo
it. More paint prep.
- 12/2: Painters prep. First staircase balluster install but it is not right.
- 12/1: Paint ceiling in hall/laundry room, 1st color coat in stairwell.
- 11/30: More staircase install, window and door trime, baseboard install.
- 11/29: Crystal Died; Baseboard install, begin staircase install. Alan sent
everyone home early.
Week 33: Doors
- 11/27:
Alan finished speaker instal, Pam painted some window screens.
- 11/26:
Knob Shopping, some speaker install
- 11/25: Alan begin speaker install
- 11/24: Hang more doors
- 11/23: Hang doors
- 11/22: Some of the doors arrive
Week 32: Sub-flooring/Trim prep
- 11/20:
Pam & Alan install fireplace logs - some heat in front of house! :)
- 11/19: Some doors arrived
- 11/18: -
- 11/17: -
- 11/16: Plumbers fixed leak in shower
- 11/15: Lay sub-flooring in kitchen, finish framing fireplace.
Week 31: Final Drywall, Prime, Interior Plumbing
- 11/12:
Plumbing moved indoors: new water heater, indoor kitchen sink and washer/dryer.
- 11/11: Prime Walls!
- 11/10:
More trenching, bit more taping/sanding etc.
- 11/9:
Trench for drainage piping, sand drywall
- 11/8: Taping/skim coat.
Week 30: Drywall Taping
- 11/6:
Pam & Alan install rubber flooring
- 11/5:
More taping, waterproof basement for leak
- 11/4: Let drywall mud dry.
- 11/3:
More drywall taping
- 11/2:
Install Exterior Trim, more drywall taping
- 11/1: Tape drywall
October
Week 29: Drywall :) and Wetfloor :(
- 10/29: Complete drywall installation.
- 10/28: More drywall installation - lower level. Dig out to find leak - problems
with water proofing.
- 10/27: Begin drywall installation - upstairs. Dig out to find leak.
- 10/26: Final rough work. After heavy rain guest room has pool of water on
floor.
- 10/25: Electrical in media room soffit. Drywall arrives.
- 10/24:
Pam/Alan make final fixes for wires etc.
Week 28: Insulation, Media Room Soffit, Final Drywall prep.
- 10/22: Misc items for drywall.
- 10/21: Hat track installation, misc items for drywall.
- 10/20: Insulation Inspection; Soffit put up; Pam/alan hung more roofing.
- 10/19: Nothing; Pam/Alan hung more roofing so soffit could be installed.
- 10/18: Finish Insullation Installation.
- 10/16-17:
Pam/Alan began hanging very heavy roofing as soundproofing.
Week 27: Final Rough + Insulation
- 10/15: Insulation installation started.
- 10/14:
Nothing.
- 10/13: Final inside framing, fireplace framing and Rough inspecation - PASSED!
- 10/12: Electrical part of day.
- 10/11: Some electrical finish-up. Plumbers fix leak under Al's office.
- 10/9-10/10:
Pam/Alan Finish running wires.
Week 26: Electrical
- 10/8: Plumbing corrections, more electrical.
- 10/7: Fireblocking, more electrical.
- 10/6: More electrical.
- 10/5: More electrical.
- 10/4: Electrical - lo voltage wiring.
- 10/2-10/3: Alan run more speaker wires minimal help from sick Pam.
September
Week 25: No Work.
- 10/1: No work - Business travel.
- 9/30: No work - Business travel.
- 9/29: No work - Business travel.
- 9/28: No work - Business travel.
- 9/27: No work - Business travel.
- 9/25-26: Pam and Alan with help from Brad run some speaker wires.
Week 24:
- 9/24:
Fireplace: complete masonry. Wire contact closures; Electrical, Stucco.
- 9/23:
Fireplace: flue and smoke chamber; Electrical.
- 9/22:
Fireplace: firebox herringbone and side walls; Electrical, HVAC.
- 9/21:
Fireplace: Inspection, pour hearth, lay firebox floor; Electrical, Stucco
wrap, Roofing repairs, some low voltage wiring
- 9/20:
Fireplace: relower floor, pour foundation; Electrical and Stucco wrap.
- 9/18-19: More fireplace prep on lower floor for Dad's arrival.
Week 23: Rough Electrical
- 9/17:
Electrical, Roofing.
- 9/16: Electrical.
- 9/15: Electrical walk through with Mark, HVAC, Plumbing.
- 9/14: HVAC/Electrical.
- 9/13:
Electrical.
- 9/11:
Pam/Alan do more fireplace prep.
Week 22: Stairs, HVAC, Electrical
- 9/10: Fireplace framing more stucco prep.
- 9/9: More HVAC, electrical, stucco prep.
- 9/8: Begin HVAC, more electrical, stucco guy visits.
- 9/7:
Stairs installed.
- 9/6: Labor Day
Week 21: Not much!
- 9/3: Nothing
- 9/2: Plumbers misc upstairs, more drain pipe & supply
- 9/1: Nothing
- 8/31: Bradley did a bit of misc framing/wall straightening and floor stiffening.
- 8/30: Frame Pantry
August
Week 20: Stairs framing, some plumbing, initial electrical
- 8-25: Some work on fixing flooring by back door.
- 8-24: More plumbing, fixed roof on dining room pump-out.
- 8-23: Stairs framed, new circuit
breaker box.
- 8-21: We installed rebar for
fireplace foundation.
Week 19: Misc framing, some plumbing.
- 8-20: Measurement for cabinets,
installed Media room window.
- 8-19: Nothing.
- 8-18: Misc framing, Stairs
measurements, plumbers.
- 8-17: Misc upstairs framing.
- 8-16: Misc lower level framing.
Week 18: More Upper Level Framing.
- 8-13: Ceiling level framing, misc items.
- 8-12: Kitchen exterior doorway
and pump-out roof. Begin rough plumbing.
- 8-11: Kitchen/Hall wall framing,
ceiling work.
- 8-10: Kitchen bump-out framing. Upper level window install.
- 8-9: Frame bathroom/laundry room walls.
- 8-8: We finished fireplace
foundation forms.
Web 17: More demo and some framing, fireplace foundation work.
- 8-7: Begin putting up forms
for fireplace foundation.
- 8-6: Frame outer stair/bathroom
wall.
- 8-5: Work on stair well.
- 8-4: Framing in the kitchen.
Big hole for the stairs.
- 8-3: Removed last bit of old
kitchen that was holding up the roof. Added roof bracing and ceiling joists.
- 8-2: More demo, some kitchen
framing
- 8-1: Dig hole for fireplace
foundation and stem wall
July
Week 16: Lower Level framing done. Upper Level Demo
- 7-30: More demo - guest room
floor, closets, all ceiling joists
- 7-29: More demo - remove stucco
for sheer walls, begin guest room demo
- 7-28: More demo - kitchen floor,
ceiling and celing joists.
- 7-27: Start main level demo
- kitchen cabinets, windows and some walls.
- 7-26: Finish lower level framing.
Week 15: Joists complete - lower level framing began.
- 7-25: More moving out of kitchen.
- 7-24: Begining to move out
of kitchen.
- 7-23: Most lower level walls
are up.
- 7-22: Lay-out locations of walls and begin putting them up.
- 7-21: Put in blocking and outer walls.
- 7-20: Hung remaining joists
- 7-19: Hung more joists.
Week 14: Begin putting up floor joists.
- 7-17: Jose cleaned-up and did
more demo since Bradley didn't show-up
- 7-16: Plumbers moved remaining
kitchen pipes - no more hot water. Gas to stove/dryer off.
- 7-15: More joists hung.
- 7-14: More joitst hung. They cut a water pipe, fixed it but then forgot
to turn the water back on :(.
- 7-13: First seven joists were installed
- 7-12: Removed stucco from side
of kitchen and prepared to add joists.
Week 13: House back on its new foundation.
- Week ending pictures.No more
cribbing downstairs!
- 7-09 Kelly Brother's House Movers comes back to remove the I-beams, cribbing, and other bracing. The house is back on a foundation! Lots of creaking and groaning as they lifted the house back up again to pull out the beams.
- 7-8 Finished framing crib walls, now the house bracing can be removed.
- 7-7 More framing.
- 7-6 The full Bauman Construction crew showed up to start framing the crib walls that the house will rest on.
- 7-5 Hmmm, still quiet. :)
June
Week 12: Finish second set of blocks and pour concrete.
- 7-2 Still quiet.
- 7-01 Ahhh, quiet! Lots of wood arrives. Short ones, tall ones, big ones, small ones.
- 6-30 Done with concreted and digging! Borns completed their work Exactly on the day as scheduled. Coincedence or good scheduling?
- 6-29 Grout poured to fill block wall. Curtis comes back with the Bobcat to remove final bits of dirt in the backyard.
- 6-28 Block wall waterproofing, more backfilling.
Week 11: Last block wall, backfilling with stone and dirt.
- 6-25 More backfilling, finished block wall.
- 6-24 Started last block wall - the window well
- 6-23 Backfill behind the block walls with stone and dirt.
- 6-22 More waterproofing, digging, and busted out the remaining slab for the old fireplace.
- 6-21 Waterproofing and some final digging to get behind the walls to waterproof.
Week 10: Finish second set of blocks and pour concrete.
- 6-12 Pictures of progress from
previous week.
- 6-14 Laid remaining blocks.
- 6-15 Set forms to tie-in existing foundation, window well rebar.
- 6-16 Window well drainage,
more forms for tie-ins.
- 6-17 Set bolts to tie-down house, inspection.
- 6-18 Poured walls, window well
foundation and patch in guest room.
- 6-19 Pictures of week's progresss
Week 9: Progress Towards Final set of blocks
- 6-7 No pictures, backfill with stones
- 6-8 Begin laying final 8"
set of blocks
- 6-9 Utility room blocks done
- 6-10 Lay more blocks, remove
bathroom plumbing, media window well forms.
- 6-11 No pictures, lay more blocks (media room area)
Week 8: Dealing with Water and Block walls Part II
- 6-1 Water proof first set of
block.
- 6-2 Install drainage.
- 6-3 Inspection of water proofing
and drainage.
- 6-4 Backfill first set of block.
May
Week 7: Block walls
- 5-24 More block laying.
- 5-25 More block laying.
- 5-26 Guess what? More block laying!
- 5-27 Final preparation for pouring
first set of block, inspection.
- 5-28 Pour first part of block.
Week 6: Progress toward walls
- 5-17 Cement block delivery (lotso
block), form removal.
- 5-18 Hand digging to allow space for drainage, form removal.
- 5-19 Initial block laying, more
misc concrete removal.
- 5-20 Block laying.
- 5-21 More block laying.
Week 5: Final preparations for and puring of slab/foundation.
- 5-10 Some rebar placed, house
movers poured pier for steel support.
- 5-11 More rebar placed.
- 5-12 Remaining rebar placed,
house movers exchanged wood pier for steel post.
- 5-13 Final set-up for pour. Inspection
passes.
- 5-14 Pour slab.
Week 4: Finalize digging, prepare for concrete
- 5-3 Sewer collapsed, temporary
sewer added. Grading and precise cutting.
- 5-4 Grading, stones and sand brought
in.
- 5-5 Form setting and rebar setting.
- 5-6 Rough plumbing.
- 5-7 First plumbing inspection. Structural Engineering/block/rebar issues
dealt with.
April
Pre-construction
- 4-03 We started by removing
the deck
Week 1: Initial Excavation
- 4-13 Patio goes away, ramp
into basement started.
- 4-14 Digging started under
house, a bit of reinforcement added to hold up the kitchen, hot water heater
moved.
- 4-15 More digging, bob cat
flips and clears foundation.
- 4-16 More digging...
- 4-17 Removal of the furnace
chimney.
Week 2: Demolition, Digging, and House Bracing
- 4-19 Begin removal of fireplace
and more digging.
- 4-20 House bracing.
- 4-21 House bracing and fireplace
removal.
- 4-22 More digging...
- 4-23 More digging and debris
cleanup from removed fireplace.
- 4-25 The brick guy...
Week 3: Digging
- 4-26 Digging, some concrete
removal. First big dumpster arrived.
- 4-27 Digging, sewer leak found.
Driveway side foundation removed.
- 4-28 Digging, driveway side
curb removed. Interior fireplace removed.
- 4-29 Some digging, house movers
reconfigure supports.
- 4-30 Media room light well
dug, large pile of dirt in back yard.