Daily Log

Click here to return to main Remodel page

November

Week 37: Tile, Cabinets, Wainscot

Week 36: Cabinets & Tile

Week 35: Cabinets, Heat

Week 34: Stairs, Trim, Paint

Week 33: Doors

Week 32: Sub-flooring/Trim prep

Week 31: Final Drywall, Prime, Interior Plumbing

Week 30: Drywall Taping

October

Week 29: Drywall :) and Wetfloor :(

Week 28: Insulation, Media Room Soffit, Final Drywall prep.

Week 27: Final Rough + Insulation

Week 26: Electrical

September

Week 25: No Work.

Week 24:

Week 23: Rough Electrical

Week 22: Stairs, HVAC, Electrical

Week 21: Not much!

August

Week 20: Stairs framing, some plumbing, initial electrical

Week 19: Misc framing, some plumbing.

Week 18: More Upper Level Framing.

Web 17: More demo and some framing, fireplace foundation work.

July

Week 16: Lower Level framing done. Upper Level Demo

Week 15: Joists complete - lower level framing began.

Week 14: Begin putting up floor joists.

Week 13: House back on its new foundation.

June

Week 12: Finish second set of blocks and pour concrete.

Week 11: Last block wall, backfilling with stone and dirt.

Week 10: Finish second set of blocks and pour concrete.

Week 9: Progress Towards Final set of blocks

Week 8: Dealing with Water and Block walls Part II

May

Week 7: Block walls

Week 6: Progress toward walls

Week 5: Final preparations for and puring of slab/foundation.

Week 4: Finalize digging, prepare for concrete

April

Pre-construction

Week 1: Initial Excavation

Week 2: Demolition, Digging, and House Bracing

Week 3: Digging